10/17/17 |
Install Water Mains & Appurtances Country Pointe Ph II (PLWD 1751) |
Plainview Water District |
|
Contractor |
Bid Amount |
|
ADJO Contracting Corp |
$282,892 |
|
G&M Earth Moving Inc |
$331,000 |
|
Merrick Utility Associates Inc. |
$364,120 |
|
Bancker Construction Corp. |
$447,985 |
|
Alessio Pipe & Construction |
$485,840 |
|
Allen Industries Inc. |
$569,140 |
|
|
|
Date |
Project Name |
Owner |
10/18/17 |
2017 West Neck Water Main Replacement Phase 3 (CIS NY#547709) |
West Neck Water District |
|
Contractor |
Bid Amount |
|
Bid A |
|
|
Bancker Construction Corp. |
$176,597 |
|
G&M Earth Moving Inc. |
$209,000 |
|
Bid B |
|
|
Bancker Construction Corp. |
$186,077 |
|
G&M Earth Moving Inc. |
$187,000 |
|
|
|
Date |
Project |
Owner |
10/19/17 |
Johnsons Lane, Chestnut St & Langdon Blvd Road Improv (PW # 14-17) |
Town of Hempstead |
|
Contractor |
Bid Amount |
|
Richard W. Grim, Inc. |
$856,907 |
|
Pratt Brothers Inc. |
$931,139 |
|
Roadwork Ahead Inc. |
$935,765 |
|
|
|
Date |
Project |
Owner |
10/25/17 |
Req Contract - Cleaning/Inspection Storm Drainage Systems (HVR17-156/PW 017-17) |
Town of Oyster Bay |
|
Contractor |
Bid Amount |
|
Thomas Novelli Contracting |
$169,400 |
|
National Water Min Cleaning Co. |
$194,132 |
|
Aarco Environmental Services Corp. |
$195,580 |
|
Earth Repair |
$198,530 |
|
Intercounty Paving Associates LLC |
$198,530 |
|
AB Environmental |
$237,408 |
|
|
|
Date |
Project |
Owner |
10/25/17 |
Highway Improvements to Smith Street Area (H16-142-PH3/PW 017-17) |
Town of Oyster Bay |
|
Contractor |
Bid Amount |
|
Rosemar Construction |
$310,765 |
|
Laser Industries Inc. |
$317,660 |
|
Intercounty Paving Associates LLC |
$323,672 |
|
Pioneer Landscaping & Asphalt Paving Inc. |
$324,100 |
|
Pratt Brothers Inc. |
$335,533 |
|
Thomas Novelli Contracting |
$353,340 |
|
PSL Industries Inc. |
$377,370 |
|
Posillico Civil |
$390,715 |
|
|
|
Date |
Project |
Owner |
10/25/17 |
Replacement of Birch Street Elevated Storage Tank (WHWD1502) |
West Hempstead Water District |
|
Contractor |
Bid Amount |
|
ELECTRICAL |
|
|
Wire to Water inc |
$196,835 |
|
Eldor Contracting Corp. |
$205,000 |
|
Palace Electrical Contractors Inc. |
$227,375 |
|
Bensin Contracting Inc. |
$242,300 |
|
Bancker Construction Corp. |
$284,700 |
|
Hinck Electrical Contractor Inc. |
$304,858 |
|
GENERAL CONTRACTOR |
|
|
Bensin Contracting Inc. |
$278,700 |
|
Phillip Ross Industries Inc. |
$368,000 |
|
Bancker Construction Corp. |
$395,800 |